Description and scope of completed work
Construction work for a film studio in Krnjača was carried out within a business complex in Belgrade. Work included the supply and installation of wall cladding on metal framing, partitions and suspended ceilings.
A total of 3,000 m² of walls, ceilings and trusses was painted. Double-leaf fire doors were installed, PVC windows were removed and fitted, and water supply and drainage systems were built.
The work included 33 m² of lightly reinforced concrete paths, 10–12 cm thick, using MB 20 concrete. Approximately 300 m² of plasterboard was used for partitions and ceilings, and 150 m² of tiles was installed.
The work took place in March 2018 and was completed in 20 days.